Sy, Do Tien and Likhitruangsilp, Veerasak and Onishi, Masamitsu and Nguyen, Phong Thanh (2016): Impacts of risk factors on the performance of public-private partnership transportation projects in vietnam. Published in: ASEAN Engineering Journal , Vol. 5, No. 1 (31 June 2016): pp. 49-71.
Preview |
PDF
MPRA_paper_96583.pdf Download (3MB) | Preview |
Abstract
The rapidly increasing demand and the inefficacy of financing transportation infrastructure project investments have contributed to various challenges for Vietnam in recent decades. Since the country’s budget is inadequate for investing in all necessary infrastructure projects, the Vietnam government has been inviting other economic sectors, especially the private sector, to participate in infrastructure development. The cooperation between the government agencies and the private entities, called Public-Private Partnership (PPP), must encounter various challenges leading to difficulties in attracting private investors. A main reason is that private investors must deal with critical risks concerning PPP investment environment. It is a challenging task for the government to optimally manage such risks to enhance the attractiveness of PPP projects for private investors. This paper examines the critical risk factors that influence the private sector’s investment decisions on PPP transportation projects in Vietnam. Risk factors inherent in typical PPP projects were compiled by comprehensive literature review. To reflect unique characteristics of PPP projects in Vietnam, the compiled risk factors were reviewed by a group of PPP experts from both the public and private sectors in Vietnam through in-depth interviews and questionnaire surveys. In addition, ten PPP project case studies in Vietnam were analyzed to derive the risk profile of PPP transportation projects of the nation. These risk factors were quantitatively assessed based on their probabilities and impact levels. We found that the critical risk factors of PPP infrastructure projects in Vietnam are acquisition/compensation problems, approvals and permits, inadequate feasibility studies, finance market issues, subjective evaluation methods, and change in laws and regulations. By performing factor analysis, these critical risk factors were grouped into four categories: (1) bidding process, (2) finance issues, (3) laws and regulations, and (4) project evaluation issues. These critical risk factors represent the obstacles that repel private investors from PPP transportation projects in Vietnam. Thus, the Vietnam government agencies should meticulously address these issues to attract both domestic and foreign private investors in PPP projects.
Item Type: | MPRA Paper |
---|---|
Original Title: | Impacts of risk factors on the performance of public-private partnership transportation projects in vietnam |
Language: | English |
Keywords: | Critical risk factors, Infrastructure, Public-Private Partnership, Risk management, Transportation projects, Vietnam |
Subjects: | R - Urban, Rural, Regional, Real Estate, and Transportation Economics > R0 - General |
Item ID: | 96583 |
Depositing User: | Dr. Phong Thanh Nguyen |
Date Deposited: | 23 Oct 2019 12:26 |
Last Modified: | 26 Oct 2019 03:12 |
References: | [1] On Investment in the Form of Build-Operate-Transfer, Build-Transfer-Operate or Build-Transfer Contract, Decree No. 108/2009/ND-CP, November 27, 2009. [2] Promulgating the Regulations on Pilot Investment in the Public-Private Partnership Form, Prime Minister Decision No. 71/2010/QD-TTg, November 9, 2010. [3] Ashurst (2012). A star in the ascendant? PPP opportunities in Vietnam, Ashurst insight:Infrastructure Opportunities. [4] Decree No. 15/2015/ND-CP on investment in the form of Public-Private Partnership. [5] T. Merna and N. J. Smith. Guide to the Preparation and Evaluation of Build-ownoperate-transfer (BOOT) Project Tenders, Asia Law & Practice Limited, 1996. [6] N. T. Toan, and K. Ozawa, ‘Stakeholders’ Perception on Risks of BOT Infrastructure Projects in Vietnam’, CIB W107 Construction in Developing Countries International Symposium, Trinidad & Tobago, 2008. [7] Y. Xu, J.F.Y. Yeung, A.P.C. Chan, D.W .M. Chan, S.Q. Wang, and Y. Ke, Developing a risk assessment model for PPP projects in China - A fuzzy synthetic evaluation approach, Automation in Construction, Vol. 19, pp. 929-943, 2010. [8] V. Ongipattanakul, Bangkok Expressway: Imminent Debt Restructuring Success. Emerging Markets Equity Research, Bangkok. Bloomberg, 1999. [9] S.Q. Wang, R.L.K. Tiong, S.K. Ting, and D. Ashley, Evaluation and management of political risks in China’s BOT projects, Journal of Construction Engineering and Management, Vol. 126, No. 3, pp. 242–250, 2000. [10] X. Zhang, Paving the Way for Public–Private Partnerships in Infrastructure Development, Journal of Construction Engineering and Management, Vol. 131, No. 1, pp. 71–80, 2005. [11] S.T. Ng, Y.M.W. Wong, and J.M.W. Wong, A Structural Equation Model of Feasibility Evaluation and Project Success for Public–Private Partnerships in Hong Kong, IEEE Transactions on Engineering Management, Vol. 57, No.2, pp. 310–322, 2010. [12] X. Zhang, Critical success factors for public-private partnerships in infrastructure development, Journal of Construction Engineering and Management, Vol. 131, No. 1, pp. 3–14, 2005. [13] Y.H. Kwak, Y. Chih, and C. W. Ibbs, Towards a Comprehensive Understanding of Public Private Partnerships for Infrastructure Development, California Management Review, Vol. 51, pp. 51-78, 2009. [14] Y. Ke, S. Wang, A. P. C. Chan, and P. T. I. Lam, Preferred risk allocation in China’s public–private partnership (PPP) projects, International Journal of Project Management, Vol. 28, No.5, pp. 482–492, 2010 [15] N.V. Thuyet, S.O. Ogunlana, and P.K. Dey, Risk management in oil and gas construction projects in Vietnam, International Journal of Energy Sector Management, Vol. 1, No.2, pp. 175–194, 2007. [16] A. Pantelias and Z. Zhang, Methodological Framework for Evaluation of Financial Viability of Public-Private Partnerships: Investment Risk Approach, Journal of Infrastructure Systems, Vol. 16, No. 4, pp. 241–250, 2010. [17] L. Qiao, S. Q. Wang, R. L. Tiong, and T.S. Chan, Framework for Critical Success Factors of BOT Projects in China, The Journal of Structured Finance, 2001. [18]M. Regan, J. Smith, and P. Love, Impact of the capital market collapse on publicprivate partnership infrastructure projects, Journal of Construction Engineering and Management, Vol. 137, No. 1, pp. 6–16, 2011. [19]L. A. El-amm, Risk Management in Toll Road Concessions, Massachusetts Institute of Technology, 2003. [20]I.D. Ozdoganm, and M. T. Birgonul, A decision support framework for project sponsors in the planning stage of build-operate-transfer (BOT) projects, Construction Management and Economics, Vol. 18, No. 3, pp. 343–353, 2000. [21]A. Dias, and P. G. Ioannou, A Desirability Model for the Development of PrivatelyPromoted Infrastructure Project, Vol. 1, 1995. [22]X. Zhang, and S. Chen, A systematic framework for infrastructure development through public private partnerships, IATSS Research, Vol. 36, No. 2, pp. 88–97, 2013. [23]W.R. Zhang, S.Q. Wang, R.L.K. Tiong, S.K. Ting, and D. Ashley, Risk management of Shanghai's privately financed Yan'an Donglu tunnels, Engineering, Construction and Architectural Management, Vol. 5, No. 4, pp. 399-409, 1998. [24]L. Shen, A. Platten, and X. Deng, Role of public private partnerships to manage risks in public sector projects in Hong Kong, International Journal of Project Management, Vol. 24, pp. 587–594, 2006. [25]A. Ng, and M. Loosemore, Risk allocation in the private provision of public infrastructure, International Journal of Project Management, Vol. 25, No.1, pp. 66–76. 2007. [26]N. Piyatrapoomi, A. Kumar and S. Setunge, Framework for Investment DecisionMaking under Risk and Uncertainty for Infrastructure Asset Management, Research in Transportation Economics, Vol. 8, pp. 199–214, 2004. [27]J. Liu, X. Yu, and C. Y. J. Cheah, Evaluation of restrictive competition in PPP projects using real option approach, International Journal of Project Management, Vol.32, No. 3, pp. 473–481, 2014. [28]N.A.R. Demong, and J. Lu, Risk-Based Decision Making Framework for Investment in the Real Estate Industry, In Handbook on Decision Making - Vol 2: Risk Management in Decision Making, J. Lu, L. C. Jain, and G. Zhang, eds: Springer-Verlag Berlin Heidelberg, pp. 259–283, 2012. [29]D. Cooper, G. Stephen, R. Geoffrey, and W. Phil, Managing Risk in Large Projects and Complex Procurements, John Wiley & Sons, England, 2004. [30]T. D Sy, Risk management for international construction joint ventures – Case studies of Vietnamese contractors. Thesis (Master), Chulalongkorn University, Bangkok, Thailand, 2011. [31]Institution of Civil Engineers and the Faculty and Institute of Actuaries (ICE), Risk Analysis and Management for Projects, Thomas Telford, London, 2005. [32]J. Pallant, SPSS Survival manual – A step by step guide to data analysis using SPSS, McGraw Hill, 2010. [33]M.J. Norusis, IBM SPSS Statistics 19 Guide to Data Analysis, Addison Wesley, Prentice Hall, 2011. [34]J.F. Hair, W.C. Black, B.J. Babin, and R.E. Anderson, Multivariate Data Analysis, Pearson, 2009. [35]N.A.A. Karim, Risk allocation in Public Private Partnership (PPP) project: a review on risk factors, International Journal of Sustainable Construction Engineering & Technology, Vol. 2, No. 2, pp. 8–16, 2011. [36] Y. Ke, S. Wang, A.P.C. Chan, and E. Cheung, Understanding the risks in China’s PPP projects: ranking of their probability and consequence, Engineering, Construction and Architectural Management, Vol. 18, No.5, pp. 481–496, 2011. [37] B.G. Hwang, X. Zhao, and M.J.S Gay, Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors, International Journal of Project Management, Vol. 31, pp. 424–433, 2013. [38] S. Ogunlana, and M.P. Abednego Case study II - Governance issues in the Yen Lenh bridge BOT project. In Public-Private Partnership in Infrastructure Development: Case Studies from Asia and Europe, H.W. Alfen, ed.: Weimar, Germany: BauhausUniversität Weimar, pp. 63–88, 2009. [39] N.D. Long, S. Ogunlana, T. Quan, and K.C. Lam, Large construction projects in developing countries: a case study from Vietnam. International Journal of Project Management, Vol. 22, No. 7, 553–561, 2004. [40] A.V. Thomas, S.N. Kalidindi, and L.S. Ganesh, Modelling and assessment of critical risks in BOT road projects, Construction Management and Economics, Vol. 24, No. 4, pp. 407–424, 2006. [41] B. Li, A. Akintoye, P.J Edward (Corresponding author), and C. Hardcastle, Critical success factors for PPP/PFI projects in the UK construction industry, Construction Management and Economics, Vol. 23, pp. 459-471, 2005. [42] M. Kert, and A.K. Izaguirre, Revival of private participation in developing country infrastructure, Public-Private Infrastructure Advisory Facility, 2007. [43] B. Flyvbjerg, M.S. Holm and S. Buhl, Cost Underestimation in Public Works Projects: Error or Lie?, Journal of the American Planning Association, Vol. 68, No. 3, pp. 279–295, 2002. [44] J. Valentine, PPP in infrastructure - Best practices from International Experience and Applications for Thailand, 2008. [45] J. Cohen, Statistical power analysis for the behavioral sciences, Hillsdale, Lawrence Erlbaum Associates, 1988. [46] N. Jabnoun, and H.H Al-Tamimi, Measuring perceived service quality at UAE commercial banks, International Journal of Quality & Reliability Management, Vol. 20, No. 4, pp. 458–472, 2003. [47] J. Ward, and J. Sussman, Analysis of the Malaysian Toll Road Public-Private Partnership Program and Recommendations for Policy Improvements. [48] V. Cuttaree, Key success factors for PPP projects based on International Experience, World Bank, Europe & Central Asia Region, St. Petersburg, 2008. [49] M. Martini, Overview of corruption and anti-corruption in Vietnam, Transparency international - towards transparency. [50] F.Y.Y Ling, and T.T.D. Bui, Factors Affecting Construction Project Outcomes - Case study of Vietnam, Journal of Professional Issues in Engineering Education and Practice, Vol. 136, No. 3, pp. 148–155, 2010. [51] T.D. Sy, and V. Likhitruangsilp, Public-Private Partnership Transportation projects in Vietnam: Opportunities and Challenges, The Twenty-Sixth KKCNN Symposium on Civil Engineering, Singapore, 2013. [52] ADB, Assessment of Public-Private Partnerships in Viet Nam. Constraints and Opportunities, Philippines: Asian Development Bank, 2012. |
URI: | https://mpra.ub.uni-muenchen.de/id/eprint/96583 |