Pulmanis, Emils (2016): Project Management in the Port Development Project in Latvia. Published in: PM World Journal , Vol. 5, No. 6 (8 June 2016): pp. 1-19.
Preview |
PDF (ImageMagick conversion from application/pdf to application/pdf)
pmwj-May2016-Pulmanis-Latvia-port_project.pdf Download (5MB) | Preview |
Abstract
Paper analyse case study of performance and compliance audit in the port development project in Latvia. Author has participated in the audit process evaluating project management application practical approach in the project implemented by the Riga Freeport Authority and co-funded by the Cohesion Fund “Development of Infrastructure on Krievu Island for the Transfer of Port Activities from the City Centre”. Despite the mass media reports that the Riga Freeport Authority has successfully completed the project, only the construction phase of the project has been completed. During the following two years the stevedore activity must be transferred to the newly built port infrastructure on Krievu Island and coal handling operations must be commenced. In order to implement these activities the stevedores have to build internal infrastructure objects, to install equipment and to restructure logistics. Furthermore, in order to obtain positive opinions from the responsible institutions on the completion of the project and attainment of the defined objectives, by March 2019 it must be proved that the project objective has been reached and the benefits must be presented. The project was initiated in 2006 when the Riga Freeport Authority made a decision on using degraded Krievu Island territories for port activities and commenced the planning estimating that the construction phase of the project would be completed by the end of 2012. In accordance with the initial plans, active cargo handling should be currently taking place in the new port territories on Krievu Island. However, the implementation of the project has delayed by almost three years (detailed project implementation timeline see as annex 1), as we see it – due to ineffective solutions to project management issues and untimely, poor communication with the parties involved in the project, such as stevedores, builders, credit institutions etc.
Item Type: | MPRA Paper |
---|---|
Original Title: | Project Management in the Port Development Project in Latvia |
English Title: | Project Management in the Port Development Project in Latvia |
Language: | English |
Keywords: | Project management, port development, Public administration, construction |
Subjects: | H - Public Economics > H4 - Publicly Provided Goods > H43 - Project Evaluation ; Social Discount Rate O - Economic Development, Innovation, Technological Change, and Growth > O2 - Development Planning and Policy > O22 - Project Analysis R - Urban, Rural, Regional, Real Estate, and Transportation Economics > R1 - General Regional Economics > R11 - Regional Economic Activity: Growth, Development, Environmental Issues, and Changes R - Urban, Rural, Regional, Real Estate, and Transportation Economics > R4 - Transportation Economics > R42 - Government and Private Investment Analysis ; Road Maintenance ; Transportation Planning |
Item ID: | 74630 |
Depositing User: | Mr. Emils Pulmanis |
Date Deposited: | 19 Oct 2016 21:21 |
Last Modified: | 26 Sep 2019 10:09 |
References: | 1.A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fourth Edition, Project Management Institute, ISBN 9781933890517, 2008., Chapter 10. Project Communications Management, pg.243-250 un A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 5th Edition, Project Management Institute, ISBN 9781628250084, 2013., Chapter 13. Project Stakeholder Management, pg.391-415. 2.JASPERS “Opinion note, Subject: Revised “Krievu Sala” project proposed by the Freeport of Riga Authority”. Warsaw, 19.06.2015., “3.1. Moving all AE activities elsewhere in the FRA area”, “3.2. The Eksportosta planned new port installations”. 3.Doran, G.T. There’s a S.M.A.R.T. Way to Write Management’s Goals and Objectives. Management Review 70.11. (Nov. 1981): 35. Business Source Corporate. EBSCO. 15 Oct. 2008. 4.R.D.Archibald, I. Di Filippo, D. Di Filippo, The Six-Phase Comprehensive Project Life Cycle Model Including the Project Incubation/Feasibility Phase and the Post-Project Evaluation Phase; skatīts 21.05.2015.: http://www.iil.com/downloads/Archibald_Di_Filippo_ComprehensivePLCModel_FINAL.pdf. 5.White Paper – European Transport Policy for 2010: time to decide, adopted by the European Commission on 12 September 2001. 6.The Riga free port environment report, 2014 Riga Free Port Authority 7.European, Latvian and Riga City transport development guidelines 8.Latvian Port Development Programme for 2008-2013, Riga Free Port Authority, 2008 9.Construction and management expert consultative opinion and evaluation reports on project implementation, “AC konsultācijas” Ltd. and “2iconsult” Ltd., 2015. |
URI: | https://mpra.ub.uni-muenchen.de/id/eprint/74630 |